2021

September 2021

Early Works Agreement

Early Works Agreement signed between Powerlink and EDF Renewables.

2022

From June 2022

Project engagement commenced

Landholder and community engagement commences.

July 2022

Drop-in session

Community information drop-in session #1.

September 2022

Drop-in session

Community information drop-in session #2.

November 2022

Draft Corridor Selection Report Released

Engagement open on the Draft Corridor Selection Report.

November 2022

Drop-in session

Community information drop-in sessions #3 .

2023

April 2023

Final Corridor Selection Report Released

Final Corridor Selection Report released. 

2024

Q1-Q3 2024

Technical studies

Technical field studies are conducted to determine transmission line easement alignment and location of proposed substation.

Q3 2024

Environmental Assessment Report (EAR)

Environmental Assessment Report (EAR) finalised and submitted to the Queensland Government as part of Powerlink’s request for Ministerial Infrastructure Designation (MID).

Q4 2024

EAR Submissions invited

Planning Minister and Powerlink invites submissions on the EAR as part of the MID process and assesses the application. 

2025

Q1 2025

Minister's decision

Planning Minister notifies of decision.

2025

Construction

If the project is approved, construction is planned to commence.