2023 - 2028

Early 2023

Engagement Activity

Commenced early engagement with landholders, Traditional Owner groups and other stakeholders

Early 2023 - current

Field and desktop studies underway

June 2024

Draft CSR

17 June - 12 July 2024

Engagement Activity

Community consultation on Draft CSR

August 2024

Final CSR

2025

Environmental approvals lodged with government agencies

Mid 2026

Planning and approvals complete

Mid 2026

Start of construction

2028

Construction complete - Start of operations