July 2024

Study area released

August 2024

Community information drop-in sessions for feedback

November 2024

Release of corridor options for feedback and community information drop-in sessions on corridor options

February 2025

Release of recommended corridor for feedback 

February-March 2025

Community information drop-in sessions – recommended corridor   

April 2025

Release of final corridor

2025

Engage with landholders to conduct on-site land studies 

2025/2026 

Easement alignment negotiations with landholders 

2026

Planning and environmental approvals lodged with government agencies 

Early 2027

Potential commencement of transmission construction