2024

end October

Transmission tower at sunset
Regulatory Milestone

Powerlink notify AER to start Framework and Approach Process

end November

Transmission tower at sunset
Regulatory Milestone

AER consult on need for Framework and Approach

mid December

Transmission tower at sunset
Regulatory Milestone

AER Notice on Framework and Approach

2025

February

Transmission tower at sunset
Regulatory Milestone

AER publish Positions Paper

June

Transmission tower at sunset
Regulatory Milestone

Powerlink lodge Expenditure Forecasting Methodology with AER

July

Transmission tower at sunset
Regulatory Milestone

AER publish Framework and Approach Paper

end September

Transmission tower at sunset
Regulatory Milestone

Powerlink publish draft Revenue Proposal

2026

end January

Transmission tower at sunset
Regulatory Milestone

Powerlink lodge Revenue Proposal with AER

March

Transmission tower at sunset
Regulatory Milestone

AER publish Issues Paper

April

Transmission tower at sunset
Regulatory Milestone

AER Public Forum on Revenue Proposal

May

Transmission tower at sunset
Regulatory Milestone

Submissions close on Issues Paper/Revenue Proposal

end September

Transmission tower at sunset
Regulatory Milestone

AER publish Draft Decision

October

Transmission tower at sunset
Regulatory Milestone

AER Pre-determination Conference

December

Transmission tower at sunset
Regulatory Milestone

Powerlink lodge Revised Revenue Proposal with AER

2027

end April

Transmission tower at sunset
Regulatory Milestone

AER publish Final Decision

January

Transmission tower at sunset
Regulatory Milestone

Submissions close on Revised Revenue Proposal

1 July

Transmission tower at sunset
Regulatory Milestone

New regulatory period starts