RIT-T for replacement expenditure planning
The Australian Energy Market Commission extended the application of the Regulatory Investment Test for Transmission (RIT-T) to replacement expenditure planning as of 18 September 2017.
Transitional arrangements
Powerlink has a number of projects that were expected to become committed during the transitional period between 18 September 2017 to 30 January 2018 and were therefore be excluded from the RIT-T process. Once the committed project criteria are fulfilled, details of any such projects are to be published on Powerlinkâs website in compliance with rule 11.99 of the National Electricity Rules.
Project name | Scheduled completion date | Project description | Project commissioned |
---|---|---|---|
Callide A/Calvale 132kV transmission reinvestment | August 2021 | At Calvale Substation establish a second 275/132kV transformer. | 30 July 2021 |
Garbutt 132/66kV transformers replacement | 30 August 2019 | At Garbutt Substation remove both of the existing transformers from service and replace with two new 100MVA 132/66kV transformers. | 25 July 2019 |
Dysart transformer replacement | July 2024 | At Dysart Substation replacement of both of the existing 132/66/22kV transformers with two new 132/66/11kV transformers. | |
Dysart primary plant replacement | 30 June 2020 | At Dysart Substation full replacement of 132kV primary plant and selected replacement of 132kV secondary systems. | October 2019 |
Line refit works on the 275kV transmission line between Woolooga and Palmwoods Substations | June 2023 | Between Woolooga and Palmwoods Substations selective replacement of 275kV steel structure components. | September 2023 |
Ashgrove West Substation replacement | June 2022 | At Ashgrove West Substation replacement of selected 110kV primary plant and secondary systems. | July 2021 |
Gin Gin Substation rebuild | June 2022 | At Gin Gin Substation replacement and reconfiguration of the 275kV and 132kV switchyards. | November 2021 |
Line refit works on the 132kV transmission line between Eton Tee and Alligator Creek Substation | December 2025 | Between Eton Tee and Alligator Creek refit and paint of the 132kV structures. | |
Calvale and Callide B secondary systems replacement | December 2024 | At Calvale Substation and Callide B Power Station replacement of the majority of 275/132kV secondary systems equipment and panels and removal of redundant equipment. |